A Tricky Wooden Puzzle at the Winterthur Cantonal Hospital

As part of a major modernization project, the Winterthur Cantonal Hospital is consolidating three of its four emergency departments under one roof. To create the new center, an existing wood-frame building was expanded upward to maximize space utilization. This required precision work down to the millimeter.

The Winterthur Cantonal Hospital (KSW) is one of the ten largest hospitals in Switzerland. It provides primary medical care for the Winterthur region and treats over a quarter of a million patients each year 
. However, the building infrastructure has begun to show its age. For example, the 15-story high-rise, which serves as the centerpiece of the complex, is already over 50 years old and no longer meets the requirements for modern hospital operations. For this reason, it is now being replaced by a new building. At the same time, other buildings on the hospital campus are being renovated, modernized, and expanded—always with the goal of utilizing the existing space as efficiently as possible.

Wooden Addition for the New Emergency Center 
As part of the expansion efforts, KSW is consolidating various emergency departments into a single center. To make room for the integration of the pediatric and adolescent emergency services, Implenia added an additional floor to the building that houses the hospital kitchen. Because the existing roof proved to have a low load-bearing capacity, the addition was constructed using timber. “Unlike a solid-structure construction, the new floor places only minimal stress on the load-bearing structure,” explains site manager Moritz Vollenweider.


, down to the millimeter . The extension was constructed using prefabricated wood elements. The exterior and interior walls were constructed using wood-frame construction, and the roof was built with horizontal glulam beams, which also transfer the load from the interior walls. Due to the length of the building, it was necessary to install localized reinforcements with steel beams.

To make full use of the newly created floor area of approximately 500 square meters, a smaller room with a gable roof was added atop the roof structure to house all the technical equipment and control systems.

Various challenges had to be overcome during construction. Because the new emergency center is bordered on three sides by other buildings, space was not the only constraint on the construction site. Rather, special attention also had to be paid to the transitions between the structures. This applied in particular to fire safety measures, which are subject to very high requirements in hospital buildings. “It was like a giant puzzle. We had to connect different fire compartments across the buildings. And since the room partitions had to be 100 percent airtight, it required precision work down to the millimeter,” explains Vollenweider.

Another major challenge was the numerous installations within the walls, such as the pneumatic tube system—which, for example, sends urine samples to the lab in seconds—or the special connections for medical equipment. “That’s why, in some cases, we were only able to fully close up the prefabricated elements on site and adapt them precisely to the equipment,” says Vollenweider.

After about ten months of construction, part of the new emergency center went into operation at the beginning of the year. Work on the existing buildings is expected to be completed by summer, so that teams from all emergency departments can begin their work.