A sustainable village in the heart of the city

Intergenerational living based on the principle of neighborly assistance—that is the goal of the TownVillage development in Winterthur. For the exterior walls and facade design, the general contractor Marti Gesamtleistungen AG is collaborating with the timber construction experts at Implenia.

With the TownVillage project, a village is essentially being created in the heart of Winterthur’s Neuhegi neighborhood. The development is designed to foster intergenerational living and aims to provide a shared home for seniors, families, single parents, and supported living groups for people with mental health challenges. The developer is the Quellenhof Foundation, which is dedicated to the reintegration of people struggling with addiction or mental illness and, to that end, provides, for example, IV-funded jobs in its workshops as well as housing.

The foundation commissioned Marti Gesamtleistungen AG to carry out the TownVillage project. As the general contractor, the company is currently constructing three new five-story buildings on the compact, approximately 10,000 m² site on Barbara-Reinhart-Strasse, which harmoniously connect the existing structures—a convention center and an old industrial building.

Precision Work Required
The buildings themselves are being constructed using traditional solid-structure methods, while the exterior wall elements and the facade are being built with wood. For this work, Marti Gesamtleistungen AG brought in the timber construction specialists from Implenia. “We are producing the exterior wall elements for all three TownVillage buildings, with the entire structure being built using a frame construction method,” explains Adrian Ulrich, project manager for timber construction at Implenia. The facade is being constructed using a mixed-construction method with durable, vertical wood formwork and lightweight Alucobond aluminum composite panels. This requires the utmost precision, as Ulrich explains: “While there’s always a certain amount of leeway with wood formwork, every millimeter counts with Alucobond. The facade panels are manufactured according to the plans and can only be minimally adjusted on-site.”

Perfect organization is essential
Ulrich cites the limited space on the site as another challenge: “As timber builders, we process an enormous amount of material on the construction site within a short period of time.” In addition, sufficient space is needed to erect the prefabricated elements. “This requires, on the one hand, nearly perfect organization, but on the other hand, a certain degree of flexibility—for example, to be able to cope with poor weather conditions. “Thanks to close collaboration, open communication, and weekly progress meetings with Marti Gesamtleistungen, as well as professional planning on both sides, we were able to meet the ambitious schedules for the first construction phase,” says Ulrich.

The TownVillage Süd building, completed during the first construction phase and featuring the foundation’s workshops and offices as well as eight apartments, has already been occupied. In August 2020, the entire development is scheduled to be handed over to the client and will then house a total of 61 apartments, a restaurant, a café, a care facility, and various event and community spaces. Upon project completion, Implenia will have installed approximately 2,500 m² of wall elements, 1,500 m² of wood facade, and about 1,800 m² of Alucobond facade.

Interview with Oliver Gruenberg, Manager of the Zurich Branch of Marti Gesamtleistungen AG