Lean Award 2026: Two winning teams with impact

What do the extension of an upper secondary school near Lausanne and a complex bridge project in Cologne have in common? In both projects, Implenia teams consistently refined their processes, made bottlenecks visible early and together developed solutions that are now showing other projects the way – with measurable results: shorter construction times and significantly lower costs. For this, they have been honoured with the Implenia Lean Award 2026.
What does the Lean Award recognise?
The Lean Award honours employees and teams who create measurable added value through Lean Thinking and Operational Excellence. It looks for initiatives that improve processes, actively involve employees in continuous improvement, achieve substantial business results and create added value for clients.
The competition was strong: 16 nominations were submitted this year, seven from the Civil Engineering Division and nine from the Buildings Division. After a pre-selection, a jury made up of the leadership teams of both divisions assessed the most effective initiatives and selected one winning project per division.
Winner Buildings Division: Team GYBUS in Bussigny
Iouri Tougarinoff and his project team are delivering the extension of the Gymnase de Bussigny, an upper secondary school. Multiple decision-makers, tight schedules and ongoing school and day-care operations made the project demanding. The team therefore relied on pull planning based on the Last Planner® System and introduced a structured process for pre-selecting subcontractors, with a detailed prequalification questionnaire for each BKP category (Swiss construction cost code).
“Above all, Lean helped us improve collaboration between the planners,” says Iouri Tougarinoff in the video. Everyone involved knew exactly when they had to release information for others. The impact:
- costs very well under control, no unforeseen problems so far
- four weeks ahead of schedule and a clear view of the time-critical work at all times
- stable forecast and lower risk of claims thanks to the early involvement of subcontractors
- Lean standards that can also be applied in future projects
Winner Civil Engineering Division: Team Mülheimer Brücke
At the Mülheimer Brücke in Cologne, Kathrin Geus and her project team demonstrated how Lean Construction works on a highly complex infrastructure project. With shopfloor management, the Last Planner® System, visual planning and structured continuous improvement, the team increased transparency, strengthened collaboration and systematically reduced waste in critical work processes. The impact:
- 33% shorter lead times for critical processes
- project schedule fully recovered
- potential to reduce unnecessary movements and transport by up to 85%
The lessons learned are being applied directly in the upcoming project phases.
Strong finalists
The other finalist teams also show impressively how versatile Lean is in practice:
- Swen Dion and team EKZ Schönbühl, Lucerne: Complete refurbishment of Switzerland’s oldest shopping centre while it remained open. Thanks to process control using a physical project model, the work was completed more than seven months earlier and the cost forecast was undercut by 30%.
- Anthony Sobreira, Mehdi Gueribiz and team Morillons, Geneva: With takt planning and weekly Lean meetings based on the Last Planner® System, the team identified obstacles early, prepared orders more efficiently and improved collaboration with the other trades.
- Michael Prager, Germany: a standardised Lean tendering process for projects using integrated project delivery (IPA). More than 100 avoidable working days identified.
- Ida Grande and team E39 Rogfast, Norway: root cause analyses, standards and visual management for rock support in tunnelling – around 50% fewer damaged rock support elements.
The Lean Award helps us make best practices visible, share experiences and inspire other teams to launch their own improvement initiatives. The nomination process for the next edition starts in November 2026.