Hall conversion with new foundation slab

Short description

Hall conversion with a new foundation slab (75 m x 25 m). Construction work in existing building.

The project

  • Construction period: 4 months
  • 460 m³ reinforced concrete
  • 175 m³ precast reinforced concrete elements
  • Foundation slab without joints measuring 75 m x 25 m
  • Construction work in existing buildings

Services in detail

  • The precast reinforced concrete supports were introduced via openings in the roof
  • The tops of the precast elements had to be aligned to within a tolerance of +/- 2 mm owing to the high requirements for the steel construction
  • High dimensional accuracy even during the reinforcement work