Krefeld
Short description
Conversion of the TKN segment workshop at the Krefeld plant.
The project
- Construction period: 4 months
- 1,200 m³ reinforced concrete
- 160 t steel construction
- 800 m² fire safety wall
- Extensive earthworks and demolition work
- Construction work in existing buildings
- Precise installation of steel elements, approx. 35 t, to +/- 5 mm
- High requirements in terms of concrete quality
- Finishing work e.g. heating/cooling/roof and façade carried out by Implenia Tesch and its partners
- Execution planning by Implenia Tesch