![[Translate to English:] Krefeld [Translate to English:] Krefeld](/fileadmin/_processed_/e/0/csm_krefeld_01_ff34d13496.jpg)
![[Translate to English:] Krefeld [Translate to English:] Krefeld](/fileadmin/_processed_/c/b/csm_krefeld_02_6787a8c84e.jpg)
![[Translate to English:] Krefeld [Translate to English:] Krefeld](/fileadmin/_processed_/f/c/csm_DSC_2320_da78e73f53.jpg)
![[Translate to English:] Krefeld [Translate to English:] Krefeld](/fileadmin/_processed_/e/0/csm_krefeld_01_ff34d13496.jpg)
![[Translate to English:] Krefeld [Translate to English:] Krefeld](/fileadmin/_processed_/c/b/csm_krefeld_02_6787a8c84e.jpg)
![[Translate to English:] Krefeld [Translate to English:] Krefeld](/fileadmin/_processed_/f/c/csm_DSC_2320_da78e73f53.jpg)
![[Translate to English:] Krefeld [Translate to English:] Krefeld](/fileadmin/_processed_/e/0/csm_krefeld_01_ff34d13496.jpg)
![[Translate to English:] Krefeld [Translate to English:] Krefeld](/fileadmin/_processed_/c/b/csm_krefeld_02_6787a8c84e.jpg)
Krefeld – civil works
Short description
Construction period of just 10 weeks for approx. 180 m of roadway including complete road construction.
The project
- Storage sewer DN 1,200 with reinforced concrete pipes
- Sewer DN 300 with concrete pipes
- Drinking water pipeline made from HDPE pipes, DN 250
- Sheet pile shoring
- Trench directly next to walkable supply channel
- Civil works with large number of interfaces to businesses
- High requirements with regard to trench backfilling with removal of the shoring elements
- Construction period of just 10 weeks for approx. 180 m of roadway including complete road construction