![[Translate to French:] Industriepark Rheinberg [Translate to French:] Industriepark Rheinberg](/fileadmin/_processed_/f/7/csm_107-0773_IMG_e2fa2a5dc8.jpg)
![[Translate to French:] Industriepark Rheinberg [Translate to French:] Industriepark Rheinberg](/fileadmin/_processed_/d/d/csm_industriepark_rheinberg_32d310ab6e.jpg)
![[Translate to French:] Industriepark Rheinberg [Translate to French:] Industriepark Rheinberg](/fileadmin/_processed_/6/a/csm_DSC_0393_bc783f5ae2.jpg)
![[Translate to French:] Industriepark Rheinberg [Translate to French:] Industriepark Rheinberg](/fileadmin/_processed_/9/1/csm_DSC_0428_2877c6ec7a.jpg)
![[Translate to French:] Industriepark Rheinberg [Translate to French:] Industriepark Rheinberg](/fileadmin/_processed_/1/a/csm_105-0591_IMG_d9a38800fb.jpg)
![[Translate to French:] Industriepark Rheinberg [Translate to French:] Industriepark Rheinberg](/fileadmin/_processed_/f/7/csm_107-0773_IMG_e2fa2a5dc8.jpg)
![[Translate to French:] Industriepark Rheinberg [Translate to French:] Industriepark Rheinberg](/fileadmin/_processed_/d/d/csm_industriepark_rheinberg_32d310ab6e.jpg)
![[Translate to French:] Industriepark Rheinberg [Translate to French:] Industriepark Rheinberg](/fileadmin/_processed_/6/a/csm_DSC_0393_bc783f5ae2.jpg)
![[Translate to French:] Industriepark Rheinberg [Translate to French:] Industriepark Rheinberg](/fileadmin/_processed_/9/1/csm_DSC_0428_2877c6ec7a.jpg)
![[Translate to French:] Industriepark Rheinberg [Translate to French:] Industriepark Rheinberg](/fileadmin/_processed_/1/a/csm_105-0591_IMG_d9a38800fb.jpg)
![[Translate to French:] Industriepark Rheinberg [Translate to French:] Industriepark Rheinberg](/fileadmin/_processed_/f/7/csm_107-0773_IMG_e2fa2a5dc8.jpg)
![[Translate to French:] Industriepark Rheinberg [Translate to French:] Industriepark Rheinberg](/fileadmin/_processed_/d/d/csm_industriepark_rheinberg_32d310ab6e.jpg)
Parc industriel Rheinberg
Brève description
Construction neuve du site de stockage de pierre calcaire en seulement six mois.
Le projet
- Durée du chantier 6 mois
- 1400 m³ de béton armé
- 300 m³ d’éléments préfabriqués en béton armé
- Tunnel de transport d’une longueur de 120 m, avec une section de 3,0 x 3,0 m
- 280 t de construction acier
- Station de transbordement souterraine avec trémie
- Livraison de pierre calcaire ou de chargement par train ou poids lourd
- Stockage intermédiaire avec un volume d’env. 10 000 m³
- Transports de matériel par un tunnel d’approvisionnement et des convoyeurs aériens