Refresh of “TORO 1” commercial building, Brown Boveristrasse 5

Zürich, Switzerland

Start of construction: August 2019

Construction volume (value of our services): 20 M CHF

The current main tenants have reduced their rental space. The vacant rental area measuring around 8,900 m², about 45% of the total rental area, is to be made available for rental to various users (multi-tenant) in future.

New building of the Kantonsspital Baden AGNES

Baden, Switzerland

Start of construction: June 2019

Construction volume (value of our services): 47,6 M CHF

New construction of a skeleton building for a new hospital. The new building with approx. 400 beds extends up to 6 upper floors.

SBB four-track expansion – Liestal

Liestal, Switzerland

Start of construction: June 2019

Construction volume (value of our services): 114,7 M CHF

Expansion of the SBB railway line from two tracks to four over a length of 2.5 km, upgrading the train station including the construction of new structures on the platform, and modifications to the infrastructure.

Spitallamm dam – Grimsel

Grimsel, Switzerland

Start of construction: May 2019

Construction volume (value of our services): 98 M CHF

The new double-curvature arch dam will be built directly in front of the existing dam. The old dam will remain in place and will be flooded at a later date.

SH4 Datacenter

Rafz, Switzerland

Start of construction: December 2019

Construction volume (value of our services): 21,5 M CHF

Construction of a data center with main building, office complex, cooling systems, generator building, 2 power conversion buildings.

Pontoons of Cologny, Geneva

Cologny, Switzerland

Start of construction: September 2019

Construction volume (value of our services): 1,8 M CHF

The attraction of this new bathing area is undoubtedly the "Great swimming Wooden Circle" on the lake which is located in front of the shore. It is the largest platform of its kind on Lake Geneva. The special attraction of this complex is the central pool opening. Bathers can enjoy the unobstructed view of the Lake Geneva Basin and its world-famous "Jet d'Eau".

AZ Rohwiesen

Opfikon, Switzerland

Start of construction: August 2019

Construction volume (value of our services): 16 M CHF

The Zurich blue-light organizations are guided by the credo "knowing heads in crisis".

South-West Bypass Brugg

Brugg/Windisch/Hausen, Switzerland

Start of construction: April 2019

Construction volume (value of our services): 3,3 M CHF

The new bypass will connect the lower Aare valley with the A1 and A3 motorways and provide access to Brugg/Windisch.

Affolternstrasse 77+79, 8050 Zurich

Zurich, Switzerland

Start of construction: January 2019

Construction volume (value of our services): 5 M CHF

Renovation and addition of another floor to the residential buildings Affolternstrasse 77/79, 8050 Zurich. The existing 31 apartments were supplemented with an additional 4 apartments with a wooden extension. The tenants could remain in the apartments during the renovation.